Which of the following indicators would help the project manager to determine the financial status of the project?

A.
CV
B. SV
C. EV
D. PV
E. COQ
F. AC
G. BAC

Correct Answer: C

Explanation:

Reference : https://pmstudycircle.com/planned-value-pv-earned-value-ev-actual-c…