An anticipated risk event occurred, and the project risk register was updated. Which of the following is the NEXT document that needs to be updated?

A.
Issue log
B. Mitigation plan
C. Milestone list
D. Project plan

Correct Answer: D

Explanation:

Reference: https://www.projectmanager.com/blog/guide-using-risk-register