CompTIA Project+ PK0-004 – Question731

A project team is ready to start working on a project; however, the project manager says the work needs to be planned first. Which of the following is MOST likely to be produced during the first planning workshop?

A.
Gantt chart
B. RACI
C. WBS
D. Risk register

Correct Answer: A