CompTIA Project+ PK0-004 – Question732

A project manager is determining the strategy and response for each risk.

Which of the following would BEST allow the project manager to complete the register? (Choose two.)

A.
Impact
B. Issue
C. Description
D. Cause
E. Probability
F. Effect

Correct Answer: AD