A project sponsor requests an urgent change to the project scope that positively impacts the performance of the end product. Which of the following should the project manager do FIRST?

A.
Ask the stakeholder to submit a change request.
B. Document the change and notify the stakeholders.
C. Change the project schedule with new estimates.
D. Notify the project team to prioritize the change.

Correct Answer: D