CompTIA Project+ PK0-004 – Question743

A project manager sends a scheduled project newsletter to all employees of the organization. Which of the following represents the communication method the project manager used?

A.
Pull
B. Interactive
C. Push
D. Asynchronous

Correct Answer: B