The burn rate of a project can be described as:

A.
how quickly a team completes a sprint in the Agile process.
B. the amount of time it takes to complete a milestone.
C. the rate at which authorized hours or budget is being used.
D. the period of time covered under the warranty of a solution.

Correct Answer: C