CompTIA Project+ PK0-004 – Question755

A regulatory project is behind schedule, and the project manager informs the steering committee that more resources are needed to complete the automation requirements on time. However, the funding request was rejected. To be in compliance, the project team performs a physical workaround to attempt to complete the project on time. Which of the following is this an example of?

A.
Risk mitigation
B. Risk acceptance
C. Risk exploitation
D. Risk avoidance

Correct Answer: D