{"id":21,"date":"2022-12-01T09:48:31","date_gmt":"2022-12-01T09:48:31","guid":{"rendered":"https:\/\/exampracticetests.com\/c\/PK0-004\/comptia-project-pk0-004-question013\/"},"modified":"2022-12-01T09:48:31","modified_gmt":"2022-12-01T09:48:31","slug":"comptia-project-pk0-004-question013","status":"publish","type":"post","link":"https:\/\/exampracticetests.com\/c\/PK0-004\/comptia-project-pk0-004-question013\/","title":{"rendered":"CompTIA Project+ PK0-004 &#8211; Question013"},"content":{"rendered":"<div class=\"question\">A project sponsor and Chief Information Officer (CIO) disagree about how to release the final deliverables to the market. The sponsor wants to do a massive product release, while the CIO wants to be extremely cautious and add more time for testing and defect resolution. The project manager works with both parties and determines the best solution is to roll the product out in a pilot release to see how it tests, and then use customer feedback to determine next steps.<br \/>\nWhich of the following conflict resolution techniques is the project manager using?<br \/><strong><br \/>A.<\/strong> Forcing<br \/><strong>B.<\/strong> Negotiating<br \/><strong>C.<\/strong> Compromising<br \/><strong>D.<\/strong> Avoiding<\/div>\n<p><\/p>\n<style> .hidden-div{ display:none } <\/style>\n<p>\t\t\t\t\t\t\t<button onclick=\"getElementById('hidden-div').style.display = 'block'\"> Show Answer <\/button> <button onclick=\"getElementById('hidden-div').style.display = 'none'\">Hide Answer<\/button><\/p>\n<div class=\"hidden-div\" id=\"hidden-div\"><span style=\"\"><\/p>\n<div class=\"answer\">Correct Answer: <strong>B<\/strong><\/div>\n<p><strong>Explanation:<\/strong> <\/p>\n<div class=\"explanation\">\nReference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 200<\/div>\n<p><\/strong><\/span> <\/div>\n","protected":false},"excerpt":{"rendered":"<p>A project sponsor and Chief Information Officer (CIO) disagree about how to release the final deliverables to the market. The sponsor wants to do a massive product release, while the CIO wants to be extremely cautious and add more time for testing and defect resolution. The project manager works with both parties and determines the [&hellip;]<\/p>\n","protected":false},"author":1,"featured_media":0,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[2],"tags":[3,16],"class_list":["post-21","post","type-post","status-publish","format-standard","hentry","category-comptia-project-pk0-004","tag-comptia-project-pk0-004","tag-question-013"],"aioseo_notices":[],"_links":{"self":[{"href":"https:\/\/exampracticetests.com\/c\/PK0-004\/wp-json\/wp\/v2\/posts\/21","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/exampracticetests.com\/c\/PK0-004\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/exampracticetests.com\/c\/PK0-004\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/exampracticetests.com\/c\/PK0-004\/wp-json\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/exampracticetests.com\/c\/PK0-004\/wp-json\/wp\/v2\/comments?post=21"}],"version-history":[{"count":0,"href":"https:\/\/exampracticetests.com\/c\/PK0-004\/wp-json\/wp\/v2\/posts\/21\/revisions"}],"wp:attachment":[{"href":"https:\/\/exampracticetests.com\/c\/PK0-004\/wp-json\/wp\/v2\/media?parent=21"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/exampracticetests.com\/c\/PK0-004\/wp-json\/wp\/v2\/categories?post=21"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/exampracticetests.com\/c\/PK0-004\/wp-json\/wp\/v2\/tags?post=21"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}