Certified Authorization Professional – CAP – Question226

What project management plan is most likely to direct the quantitative risk analysis process for a project in a matrix environment?

A.
Staffing management plan
B. Risk analysis plan
C. Human resource management plan
D. Risk management plan

Correct Answer: D