All projects involve some extent of change, because they involve work that is unique in some fashion. Therefore, it is important that a project management plan includes a______________.
A. Description of the change request process
B. Configuration management plan
C. Methodology for preventive action to avoid the need for excessive changes
D. A work authorization system
A. Description of the change request process
B. Configuration management plan
C. Methodology for preventive action to avoid the need for excessive changes
D. A work authorization system