Project Management Professional (PMP) Exam Practice – Question0042

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?


A.
0.03
B. 0.06
C. 0.10
D. 0.50

Correct Answer: B