Project Management Professional (PMP) Exam Practice – Question0042 What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)? A. 0.03 B. 0.06 C. 0.10 D. 0.50 Show Answer Hide Answer Correct Answer: B