Project Management Professional (PMP) Exam Practice – Question0256

A project manager assumes a new project. As part of the initiation process, what should the project manager do prior to the planning stage?


A.
Define the project sign-off criteria and create a risk register.
B. Develop the project charter and identify the stakeholders.
C. Start gathering requirements and plan the kick-off meeting.
D. Acquire the resources and determine the budget.

Correct Answer: C