A project manager assumes a new project. As part of the initiation process, what should the project manager do prior to the planning stage?
A. Define the project sign-off criteria and create a risk register.
B. Develop the project charter and identify the stakeholders.
C. Start gathering requirements and plan the kick-off meeting.
D. Acquire the resources and determine the budget.
A. Define the project sign-off criteria and create a risk register.
B. Develop the project charter and identify the stakeholders.
C. Start gathering requirements and plan the kick-off meeting.
D. Acquire the resources and determine the budget.