Project Management Professional (PMP) Exam Practice – Question0486

A project team member wants to ensure that deliverables are compliant with the requirements. To accomplish this, the team decides to review the multiple results of the tests performed on different deliverables. The project manager is concerned that this process
will affect the time assigned to these verification activities.

What should the project manager use for the review?


A.
Ishikawa diagram and statistical sampling
B. Statistical sampling and checksheets
C. Checksheets and Pareto diagrams
D. Control charts and scatter diagrams

Correct Answer: B