A project has a budget of US$900. Its estimate to complete (ETC) is US$600, the budget at completion (BAC) is $US800, and the estimate at completion (EAC) is US$1,200.
What is the management reserve?
A. US$100
B. US$200
C. US$300
D. US$400
What is the management reserve?
A. US$100
B. US$200
C. US$300
D. US$400