A project manager estimates project costs and uses three different estimates to assess the approximate cost for an activity. What type of estimating technique did the project manager use?
A. Bottom-up
B. Beta distribution
C. Analogous
D. Parametric
A. Bottom-up
B. Beta distribution
C. Analogous
D. Parametric