Project Management Professional (PMP) Exam Practice – Question0514

A project manager estimates project costs and uses three different estimates to assess the approximate cost for an activity. What type of estimating technique did the project manager use?


A.
Bottom-up
B. Beta distribution
C. Analogous
D. Parametric

Correct Answer: B