A project's outcome is highly sensitive to and dependent upon financial market activity. Therefore, the companys financial advisor delivers daily exchange-rate forecasts. The project's budget was planned using a conservative scenario with high exchange-rate
variations. The project manager now wants to review this budget to update the probability and impact of a possible new scenario using current financial conditions.
To what should the project manager refer?
A. Stakeholder register
B. Risk register
C. Lessons learned
D. Marketplace conditions
variations. The project manager now wants to review this budget to update the probability and impact of a possible new scenario using current financial conditions.
To what should the project manager refer?
A. Stakeholder register
B. Risk register
C. Lessons learned
D. Marketplace conditions