Project Management Professional (PMP) Exam Practice – Question0515

A project's outcome is highly sensitive to and dependent upon financial market activity. Therefore, the companys financial advisor delivers daily exchange-rate forecasts. The project's budget was planned using a conservative scenario with high exchange-rate
variations. The project manager now wants to review this budget to update the probability and impact of a possible new scenario using current financial conditions.
To what should the project manager refer?


A.
Stakeholder register
B. Risk register
C. Lessons learned
D. Marketplace conditions

Correct Answer: D