Project Management Professional (PMP) Exam Practice – Question0533

A key stakeholder is unhappy with a projects unrealistic timeline. At the project plan review and approval meeting, the stakeholder refuses to support the project.
What should the project manager do to ensure that the stakeholder will approve the proposed project timeline?


A.
Submit the project management plan to the customer for approval and begin implementation.
B. Make certain that this stakeholder is fully engaged and involved during the planning phase.
C. Ensure that all key stakeholders are involved in resolving the proposed timeline issue prior to seeking approval.
D. Proceed with the project management plan if the majority of stakeholders involved in the planning stage agree.

Correct Answer: C