Project Management Professional (PMP) Exam Practice – Question0591

Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?


A.
Control Schedule
B. Define Activities
C. Develop Schedule
D. Estimate Activity Resources

Correct Answer: D