Project Management Professional (PMP) Exam Practice – Question0666

After Define Activities and Sequence Activities, the next process is:


A.
Estimate Activity Resources.
B. Estimate Activity Durations.
C. Develop Schedule.
D. Control Schedule.

Correct Answer: B