After Define Activities and Sequence Activities, the next process is:
A. Estimate Activity Resources.
B. Estimate Activity Durations.
C. Develop Schedule.
D. Control Schedule.
A. Estimate Activity Resources.
B. Estimate Activity Durations.
C. Develop Schedule.
D. Control Schedule.