Project Management Professional (PMP) Exam Practice – Question0776

A project manager for a US$15 million construction project must meet a specific project milestone earlier than planned because a season-long pattern of extreme weather is expected soon. The project is already over budget, and the project sponsor is not
prepared to provide additional funding.

Which tool or technique should the project manager use to achieve the milestone before the extreme weather begins?


A.
Simulation
B. Fast tracking
C. Resource smoothing
D. Crashing

Correct Answer: B