Project Management Professional (PMP) Exam Practice – Question0778

During a project that affects the entire organization, some groups of stakeholders appear to have low product expectations. As a result, they are not performing as expected. This may put project objectives at risk.
What should the project manager do?


A.
Ask the project sponsor to intervene and motivate the underperforming stakeholders.
B. Follow the stakeholder engagement plan.
C. Submit a change request.
D. Speak with the problematic stakeholders to increase their performance.

Correct Answer: B