A project team member encounters an issue and identifies a workaround, but fails to inform the project manager. Two weeks later, a similar issue occurs that impacts the project.
What could have prevented this issues reoccurrence?
A. Documenting the organizational process assets
B. Revising the responsibility assignment matrix (RAM)
C. Performing a root cause analysis
D. Updating the risk register
What could have prevented this issues reoccurrence?
A. Documenting the organizational process assets
B. Revising the responsibility assignment matrix (RAM)
C. Performing a root cause analysis
D. Updating the risk register