A project has a time and material (T&M) contract with a third-party vendor. The project manager discovers that the law has changed, and that the current terms and conditions are no longer valid.
What should the project manager perform next?
A. Claims Administration
B. Conduct Procurements
C. Control Procurements
D. Manage Stakeholder Engagement