Midway through project implementation, stakeholders lose confidence in project management and want to withdraw. What should the project manager use to maintain and improve relationships with the stakeholders?
A. Interactive communication
B. Detailed project status reporting
C. Pull communication
D. Power/influence grid evaluation
A. Interactive communication
B. Detailed project status reporting
C. Pull communication
D. Power/influence grid evaluation