Project Management Professional (PMP) Exam Practice – Question0799

An issue requires the execution of the projects contingency plan, which impacts the schedule. What should the project manager do?


A.
Initiate a risk audit.
B. Issue a change request.
C. Review the cost impact.
D. Update the contingency plan.

Correct Answer: C