Project Management Professional (PMP) Exam Practice – Question0814

A project management office (PMO) assigns a resource to a project. To what should the project manager refer to evaluate this resource?


A.
Expert judgement
B. Responsible, accountable, consult, and inform (RACI) matrix
C. Resource management plan
D. Resource requirements

Correct Answer: C