A project management office (PMO) assigns a resource to a project. To what should the project manager refer to evaluate this resource?
A. Expert judgement
B. Responsible, accountable, consult, and inform (RACI) matrix
C. Resource management plan
D. Resource requirements
A. Expert judgement
B. Responsible, accountable, consult, and inform (RACI) matrix
C. Resource management plan
D. Resource requirements