Project Management Professional (PMP) Exam Practice – Question0882

A strike at a contracted production plant affects the delivery of a projects major deliverable and impacts project objectives. To what should the project manager refer to address this issue?


A.
Standardized bid documents
B. Managing multiple suppliers documents
C. Procurement statement of work (SOW)
D. Risk response plan

Correct Answer: D