Project Management Professional (PMP) Exam Practice – Question1053

Which process occurs within the Monitoring and Controlling Process Group?


A.
Cost Control
B. Quality Planning
C. Quantitative Risk Analysis
D. Cost Budgeting

Correct Answer: A