Project Management Professional (PMP) Exam Practice – Question1053 Which process occurs within the Monitoring and Controlling Process Group? A. Cost Control B. Quality Planning C. Quantitative Risk Analysis D. Cost Budgeting Show Answer Hide Answer Correct Answer: A