Project Management Professional (PMP) Exam Practice – Question1068

Which of the following is a schedule network analysis technique that takes limited resources into account?


A.
Network reserve analysis
B. Critical chain method
C. Lead and lag adjustment
D. Critical path method

Correct Answer: B