Project Management Professional (PMP) Exam Practice – Question1091

A projects primary focus is staying on schedule. To monitor this, the project manager requests monthly progress reports from the contractor.
What should the project manager ask the contractor to include in these reports?


A.
Gantt chart
B. Work breakdown structure (WBS)
C. Network chart
D. Schedule attributes

Correct Answer: A