Project Management Professional (PMP) Exam Practice – Question1092

During project implementation, the project manager reviews identified key performance indicators (KPIs) and determines that the project is within budget and on schedule. To what process does this activity belong?


A.
Review Scope Baseline
B. Review Project Performance
C. Perform Integrated Change Control
D. Monitor and Control Project Work

Correct Answer: D