During project implementation, the project manager reviews identified key performance indicators (KPIs) and determines that the project is within budget and on schedule. To what process does this activity belong?
A. Review Scope Baseline
B. Review Project Performance
C. Perform Integrated Change Control
D. Monitor and Control Project Work
A. Review Scope Baseline
B. Review Project Performance
C. Perform Integrated Change Control
D. Monitor and Control Project Work