A project team member identifies a quality issue that may cause the product to be rejected by the customer. However, the project sponsor wants to deliver the product.
What should the project manager do?


A.
Update the issue log.
B. Deliver the product.
C. Review the quality checklist.
D. Ensure that the product meets customer requirements.

Correct Answer: C