During which process would stakeholders provide formal acceptance of the completed project scope?
A. Perform Quality Control
B. Verify Scope
C. Control Scope
D. Develop Schedule
A. Perform Quality Control
B. Verify Scope
C. Control Scope
D. Develop Schedule