Project Management Professional (PMP) Exam Practice – Question1346

Each WBS component should be assigned a unique identifier from a code of accounts to______________


A.
Link the WBS to the bill of materials
B. Enable the WBS to follow a similar numbering system to that of the organization's units as part of the organizational breakdown structure
C. Sum costs, schedule, and resource information
D. Link the WBS to the project management plan

Correct Answer: C

Explanation:

Explanation:
The key document generated from the create WBS process is the actual WBS. Each WBS component is assigned a unique identifier to provide a structure for hierarchical summation of costs, schedule, and resource information.