Project Management Professional (PMP) Exam Practice – Question1390

A schedule performance index of less than 1.0 indicates that the______________


A.
Project is running behind the monetary value of the work it planned to accomplish
B. Earned value physically accomplished thus far is 100%
C. Project has experienced a permanent loss of time
D. Project may not be on schedule, but the project manager need not be concerned

Correct Answer: A

Explanation:

Explanation:
The SPI represents how much of the originally scheduled work has been accomplished at a given period in time, thus providing the project team with insight as to whether the project is on schedule.