A schedule performance index of less than 1.0 indicates that the______________
A. Project is running behind the monetary value of the work it planned to accomplish
B. Earned value physically accomplished thus far is 100%
C. Project has experienced a permanent loss of time
D. Project may not be on schedule, but the project manager need not be concerned
A. Project is running behind the monetary value of the work it planned to accomplish
B. Earned value physically accomplished thus far is 100%
C. Project has experienced a permanent loss of time
D. Project may not be on schedule, but the project manager need not be concerned