All the following statements regarding critical chain method are true EXCEPT______________
A. It modifies the schedule to account for limited resources
B. The first step is to use conservative estimates for activity durations
C. Duration buffers are added on the critical path
D. It focuses on managing buffer activity durations
A. It modifies the schedule to account for limited resources
B. The first step is to use conservative estimates for activity durations
C. Duration buffers are added on the critical path
D. It focuses on managing buffer activity durations