All the following statements regarding critical chain method are true EXCEPT______________


A.
It modifies the schedule to account for limited resources
B. The first step is to use conservative estimates for activity durations
C. Duration buffers are added on the critical path
D. It focuses on managing buffer activity durations

Correct Answer: B

Explanation:

Explanation:
When using critical chain techniques, the initial project schedule is developed using duration estimates with required dependencies and defined constraints as inputs.