When choosing the most appropriate form of project organization, the first step is to______________
A. Create the WBS and let it determine the project organizational structure
B. Produce a project management plan and determine the functional areas responsible for each task
C. Refer to the project charter developed by top management
D. Develop a project schedule, including a top-down flowchart, and identify the functional areas to perform each task