Project Management Professional (PMP) Exam Practice – Question1525

When choosing the most appropriate form of project organization, the first step is to______________


A.
Create the WBS and let it determine the project organizational structure
B. Produce a project management plan and determine the functional areas responsible for each task
C. Refer to the project charter developed by top management
D. Develop a project schedule, including a top-down flowchart, and identify the functional areas to perform each task

Correct Answer: B

Explanation:

Explanation:
All effort on a project starts from the project management plan, which details the work that must be accomplished. It is a key input as the human resource management plan is developed.