Project Management Professional (PMP) Exam Practice – Question1572

Projects are particularly susceptible to risk because______________


A.
Murphy's law states that "if something can go wrong, it will"
B. There is uncertainty in all projects
C. Project management tools are generally unavailable at the project team level
D. There are never enough resources to do the job

Correct Answer: B

Explanation:

Explanation:
Every project has uncertainty associated with it because a project by its definition is a temporary endeavor undertaken to create a unique product, service, or result. Risks may be known or unknown.