Project Management Professional (PMP) Exam Practice – Question1680

Having prepared stakeholder management plans on previous projects, you know it is positive to review the project management plan because it______________


A.
Provides information as to how to plan appropriate ways to engage stakeholders
B. Contains information useful to ensure the stakeholder management plan is aligned with the organization's culture
C. Helps to determine the best options to support an adaptive process for stakeholder management
D. Contains a change management plan and documents how changes will be monitored and controlled

Correct Answer: D

Explanation:

Explanation:
Among other key items useful in the project management plan to review while preparing the stakeholder management plan is the change management plan. All projects involve some type of change. Reviewing this plan can help the project manager work with
stakeholders who may be resistant to the project to help turn them into ones who are supportive or at least neutral to the resulting changes.