Project Management Professional (PMP) Exam Practice – Question1745

One output of the control costs process is cost forecasts, which is when______________


A.
Modifications are made to the cost information used to manage the project and are communicated to stakeholders
B. Trend analyses are performed and communicated to stakeholders
C. A budget update is required and communicated to all stakeholders
D. A calculated EAC value or a bottom-up EAC value is documented and communicated to stakeholders

Correct Answer: D

Explanation:

Explanation:
Cost forecasts are another output of control costs, and the EAC is used to show the expected total costs of completing all work expressed as the sum of the actual cost to date and the estimate to complete.