Project Management Professional (PMP) Exam Practice – Question1795

You are the project manager for a major logistics installation project and must obtain specific services from local sources external to your project. Your subcontracts administrator has told you to prepare a product or service description, which is referenced in
a______________


A.
Project statement of work
B. Contract scope statement
C. Request for proposal
D. Contract

Correct Answer: A

Explanation:

Explanation:
The project statement of work describes in a narrative form the products, services, or results that the project will deliver. It references the product scope description as well as the business need and strategic plan.